Topical snapshot of the property file — every material element of the scheme as scannable cards, each with the underlying source cited beneath. Green left-bar = primary-source confidence; amber = secondary evidence only.
01 · LOTS
Lot count
247 lots · 10,000 aggregate UE. Plan registered 19 Sep 2017. Lot 248 = Shop1 (commercial). SP 97558 is a subdivision of common property of head plan SP 90191 — not a separate adjacent scheme.
Source: CWF Plan 2018 · Insurance Valuation 2025
02 · STOREYS
Building height
4 buildings, 6–10 storeys + 1 basement. Building A reaches Level 8. Construction date 2017 — cavity brick, part rendered, part metal clad, concrete floors.
Source: Insurance Valuation · AFSS 2025
03 · BASEMENT
Basement carpark
1 basement level containing the carpark. Currently subject to defect rectification works (basement flooding scope-of-works under preparation).
Source: AFSS 2025 · Insurance Valuation
04 · ADMIN FUND
Administrative Fund balance
($73,385) deficit as at 24 April 2026 — primarily a timing issue (Q4 levies not yet raised). Projected year-end: $223,700.
Source: Detailed Balance Sheet 24/04/2026 · Audit FY24
05 · CWF
Capital Works Fund balance
$333,629 as at 24 April 2026. Cash $483k, investments $0 (fully redeemed), liabilities $151k. Net Owners Funds down 56% in 9 months.
Source: Detailed Balance Sheet · Investments section
06 · SPECIAL LEVIES
Special levies
Yes — $1,160,000 inc GST authorised by EGM 16/02/2026 Motion 7, in 4 instalments May 2026 → Feb 2027. Funds defects litigation costs.
Source: General Meeting Minutes 16/02/2026
07 · ARREARS
Levy arrears
$7,627 total across 6 lots. Lots 103 and 190 account for over 90%. Grace Lawyers Pty Ltd handling recovery against 12 lots.
Source: Aged Arrears List 24/04/2026
08 · CWF PLAN
10-year capital works plan
Yes — 15-year plan dated 4 June 2018 by Sageview NSW. Materially out of date (almost 8 years old) — past the s80 5-year review interval.
Source: Capital Works Fund Plan 2018
09 · STRATA MGR
Strata manager
Strata Choice Pty Ltd · Mark Loveridge (Lic 224770) · 1300 322 213 · info@stratachoice.com.au · SMA dated 01/10/2025, term 36 months, $45,695 inc GST p.a.
Source: Signed Agency Agreement
10 · BLDG MGR
Building manager
Sydney Building Management & Projects (SBMP) trading as Apartment Projects Pty Ltd · ABN 14 167 332 069 · 02 9056 7100 · info@sydneybmp.com.au.
Source: SBMP Tax Invoice INV-12795
11 · WINDOW SAFETY
Window safety devices
No formal WSR on file. Only AS1891 height-safety inspection (for window cleaners' anchor points) by Advanced Solutions Group, 2 Aug 2023 — different compliance regime.
Source: ASG Tax Invoice I3838
12 · CLADDING
External cladding
No ACP cladding — definitive per Insurance Valuation 6 Aug 2025. Construction is "Cavity Brick, Part Rendered, Part Metal Clad" — not the high-risk ACP/PE.
Source: Insurance Valuation A G Thomas
13 · ASBESTOS
Asbestos register
Not required — building constructed 2017, well after 31 December 2003 Australia-wide ban on asbestos products.
Source: WHS Reg 2017 · Construction date confirmed
14 · PEST
Pest inspection
No formal report; treatment records only (Greenway Pest Control, quarterly). Bee infestation treated at Units 1701 & 1801 Kona A in 2023.
Source: Greenway service records
15 · DEFECTS
Building defects
Extensive — across all 4 buildings. Hydraulic, fire & life safety, basement flooding, façade, acoustic. 191 units (78%) affected by failed waterproofing. See sections 5–7.
Source: 7+ expert reports · EGM Minutes
16 · FIRE SAFETY
Fire safety services
AFSS 2025 lodged 30/07/2025 by accredited practitioner F049448A. ARUP Fire Engineering Report 247294 Rev E from original construction. Ongoing fire defects investigation.
Source: AFSS T0796-AFSS-2025
17 · CAPITAL WORKS
Capital works program
Extensive — $259,545 newly authorised at EGM. Ceerose actively rectifying Units 2716, 3206, 1801. No FY 2026–27 forward budget yet struck.
Source: EGM Minutes · I&E Statement
18 · LITIGATION
Litigation
Yes — three live matters. NSW Supreme Court (Proc 2023/315882) v Ceerose & Galileo · NCAT (Proc 2025/00296898) Farrugia v OC · plus threatened NCAT claim Lot 233.
Source: Court records · Chambers Russell email 14/11/2025
19 · DA / CDC
Development applications
No formal DA/CDC lodged. Active DA-requirement enquiry with Inner West Council for installation of bollards. Internal renovation approvals (Units 5002, 2305, 2102, 1509) are by-law minor renovations, not DAs.
Source: Inventory emails · Consolidated By-Laws